Shipment of 4 Scrubbers from Volgograd within the UGTL project

Uzbekistan GTL is a plant for the production of synthetic liquid fuels under construction in the south-west of Uzbekistan in the Kashkadarya region. The raw material base for the future plant will be purified methane produced by the Shurtan Gas Chemical Complex, located at a distance of 1.5 km. The plant under construction in Uzbekistan will be the third in the world plant for the production of synthetic liquid fuels based on the Sasol Gas-to-liquids technology (gas to liquid). To date, the construction of the plant has entered the active phase. Commissioning of the plant is scheduled for the second half of 2020.

General Contractor (EPC): Hyundai Engineering Co. Ltd.,Hyundai Engineering and Construction Co., Ltd (Korea) and Enter Engineering Pte. Ltd. (Singapore)

As part of the project on transportation of OOG equipment for the construction of high-quality fuel plant "OLTIN YO'L GTL" (UzGTL), project team of Barrus Projects successfully performed shipment of 4 units of oversized equipment from Volgograd, Russian Federation for delivery to port of Kuryk, Republic of Kazakhstan.

  1. Nitrogen scrubber (72mt / 19,5 7,2 6,6)
  2. Nitrogen scrubber (72mt / 19,5 7,2 6,6)
  3. Air scrubber (144mt / 27,8 7,45 6,85)
  4. Air scrubber (144mt / 27,8 7,45 6,85)

After delivery of Equipment to the territory of Republic of Kazakhstan, this equipment will be delivered by forces of Barrus Projects to Consignee at a job site.